Slab, column, or step dimensions to cubic yards and 40/60/80 lb bags.
🧱 At 4 inches thick, one cubic yard covers 81 ft². Past about a full yard (≈45 eighty-lb bags) order ready-mix by the truck — hand-mixing 20+ bags is a day of its own.
The Concrete Calculator is based on the following formula:
Slab: V(ft³) = L × W × (T ÷ 12) Column: V = π × (D ÷ 24)² × H × n Steps: V = n × (run × rise ÷ 2) × W ÷ 144 Order volume = V × (1 + waste%) · yd³ = order volume ÷ 27 Bags = ⌈order volume ÷ yield⌉ (80 lb = 0.60 ft³, 60 lb = 0.45 ft³, 40 lb = 0.30 ft³)
Variables: L, W = slab length and width (ft) T = slab thickness (in, converted to feet by ÷12) D = column diameter (in; radius in feet = D ÷ 24) · H = column height (ft) · n = number of columns run, rise = step tread depth and riser height (in) · W = step width (ft) waste% = spill/cut allowance (e.g. 10) yield = hardened volume one bag produces (ft³)
All shapes reduce to volume in cubic feet; thickness in inches converts by dividing by 12. The waste margin is applied before any conversion, and every bag count rounds up because partial bags cannot be bought.
Worked example: Step 1: Slab 10 ft × 8 ft at 4 in thick: V = 10 × 8 × (4 ÷ 12) = 26.67 ft³. Step 2: Add 10% waste: 26.67 × 1.10 = 29.33 ft³ = 29.33 ÷ 27 = 1.09 yd³. Step 3: 80 lb bags = ⌈29.33 ÷ 0.60⌉ = 49. Step 4: 60 lb bags = ⌈29.33 ÷ 0.45⌉ = 66; 40 lb bags = ⌈29.33 ÷ 0.30⌉ = 98. Result: order 1.09 yd³ — or 49 eighty-pound bags for the same pour.
Concrete is ordered in cubic yards (27 ft³ each), but sold retail in bags: an 80 lb bag yields 0.60 ft³, a 60 lb bag 0.45 ft³, a 40 lb bag 0.30 ft³. A 10×10 slab at 4 inches is 33.3 ft³ — 1.23 yards, or 62 eighty-lb bags once the 10% margin is in.
At 4 inches thick, one yard covers exactly 81 ft². That single conversion prices any patio: 20×20 is 400 ÷ 81 ≈ 5 yards. Past one yard the math favors a ready-mix truck — 45 bags of Quikrete is a full day of mixing.
Round footings are π × (diameter ÷ 2)² × height — a 12-inch-by-3-foot Sonotube is 2.36 ft³, about 5 bags including waste. Steps pour as triangular prisms: tread run × rise ÷ 2, times width, per step.
Short loads and second trips cost more than surplus. The 10% margin covers spills and uneven subgrade; if your forms are hand-dug and wavy, 15% is the honest number.
More tools you might find useful
Deck size and board width to board count, linear feet, and joists.
Wall and ceiling area to sheets, screws, and joint compound.
Perimeter and post spacing to posts, pickets, rails, and concrete.
Room size + waste factor → boxes needed and material budget (ft²/m²).