Patio area to paver count plus base gravel and bedding sand.
🧱 Coverage runs 4.5 pieces per ft² for 4×8, 4 for 6×6, 2.25 for 8×8 and 1 for 12×12. Base depth follows traffic: 4″ for patios and paths, 6-12″ under driveways. Bedding sand stays at 1″ — thicker sand beds creep, rut, and wreck the surface.
The Paver Calculator is based on the following formula:
pavers = ⌈L × W × (pieces per ft²) × (1 + waste%)⌉ pieces per ft²: 4×8 = 4.5 · 6×6 = 4 · 8×8 = 2.25 · 12×12 = 1 gravel yd³ = L × W × (base depth ÷ 12) ÷ 27 sand yd³ = L × W × (1 ÷ 12) ÷ 27
Variables: L, W = patio length and width (ft) pieces per ft² = published coverage of the paver size waste% = cutting allowance (10 for straight patterns, 15 for diagonal) base depth = compacted crushed stone thickness (in), typically 4-6 1 = bedding sand thickness (in) — never thicker
Piece count is area times the per-foot coverage of the chosen size, padded by the waste factor and rounded up. Base volumes convert depth in inches to feet, divide by 27 to yards, with bedding sand fixed at one inch.
Worked example: Step 1: Patio 16 ft × 12 ft: area = 192 ft². Step 2: 4×8 pavers with 10% waste: ⌈192 × 4.5 × 1.10⌉ = ⌈950.4⌉ = 951. Step 3: Gravel base 4 in: 192 × (4 ÷ 12) = 64 ft³ = 64 ÷ 27 = 2.37 yd³. Step 4: Bedding sand 1 in: 192 × (1 ÷ 12) = 16 ft³ = 0.59 yd³. Result: 951 pavers on 2.37 yd³ of base and 0.59 yd³ of sand.
Concrete pavers come in fixed sizes, so coverage is a published constant: 4.5 pieces of 4×8 per square foot, 4 of 6×6, 2.25 of 8×8, 1 of 12×12. A 16×12 patio with 4×8s needs 864 pieces exactly — 951 with a 10% cutting allowance.
Pavers fail from below, not above. Patios and walkways want 4 inches of compacted crushed stone; driveways want 6-12 with geotextile under it. For 192 ft² at 4 inches that's 64 ft³ — 2.37 yards of crushed stone delivered.
Bedding sand is a screeding layer, not a leveling crutch: exactly 1 inch of coarse concrete sand. Thicker beds pump water, creep under load, and rut within a season. Joints get polymeric sand swept in after compaction.
Straight-laid running bond trims 10%; herringbone and 45° diagonals cut more edges, so allow 15%. Buy all pavers from one pallet run — like tile and drywall, dye lots differ visibly across batches.
More tools you might find useful
Gallons and liters for rect, round, or kidney pools — plus turnover time.
How much soil your bed needs — with Mel's Mix and budget blend recipes.
Footprint times pitch factor to squares, bundles, and felt rolls.
Count strips, not square feet — rolls with pattern repeat, doors, and windows.